In early June, crews pushed two wick drains into the north embankment below the Lake & Spruce Bridge on Lake Road. The drains were meant to pull water out of the slope and keep it from wearing away further. They have kept running at about 64 ounces a minute, which is half a gallon, and they show no sign of slowing.
That steady flow explains why one stretch of Lake Road is still closed this fall. A few blocks away, the new Lake & Woodbine Bridge has been finished and celebrated. The holdup at Spruce has very little to do with the bridge. The ground under it is the issue, and the City has decided to measure that ground carefully before it builds anything permanent on it.
A Bridge Repair That Became a Ravine Problem
The Lake & Spruce Bridge sits between Woodland Road and Spruce Avenue. City documents also call it the McLennon-Reed Bridge. It went up in 1978, and over the decades its deck has been patched with epoxy, concrete and asphalt. The plan was a straightforward rehab: a new concrete deck across three steel spans totaling 173 feet, new railings, a sidewalk along the east edge, and about 33 feet of slope repair directly beneath the bridge.
On November 17, 2025, the City Council awarded the job to Dunnet Bay Construction for $2,175,000. When the contractor started in March 2026, the project team saw an abnormal amount of water draining from the north ravine embankment. The wick drains went in that June. When they kept discharging, City staff halted the rehab out of concern about saturated soil and possible slope failure. The City then brought in ECS Midwest for emergency subsurface exploration, and the Council ratified that contract on July 20.
ECS drilled four soil borings, each 100 feet deep. They found groundwater about 24 feet below grade in a sand layer. The borings could not show whether that water is a local pocket or runs all the way down the slope to the bottom of the ravine. ECS concluded that both ravine slopes are stable in the short term. To meet the required long-term safety standard, though, both will need stabilization.
In short, the slopes are not in danger right now, and nobody yet knows exactly where the water comes from.
Why the City Is Paying to Measure Again
ECS's August report did not settle the design. City staff judged its groundwater assumptions too conservative to engineer from. Building to those assumptions would mean more stabilization than the ravine may need, and a higher bill.
So at its October 5 meeting, the Council approved a contract amendment of up to $70,300 with Wiss, Janney, Elstner Associates. The firm will coordinate more subsurface investigation and run a new slope stability analysis. The vote was 6–0, with one abstention. WJE was already on the project as the City's bridge program manager.
The money tells you how much the City has at stake. The amendment uses up the project's remaining contingency of about $5,569. The other $64,731 was not budgeted, and staff expect to cover it from FY2027 Capital Improvement Fund savings. Staff told the Council that the eventual stabilization could cost anywhere from six to seven figures. With a range that wide, spending about $70,000 to narrow it before anyone pours concrete is a reasonable bet.
Woodbine Finished, and That Opened the Door at Spruce
The two projects share a contractor and a calendar. During the October 5 presentation, staff explained that with Lake & Woodbine complete, Dunnet Bay could move back to Spruce as early as the following week to start winter stabilization of the ravine channel. Getting Woodbine done is what lets work resume at Spruce.
Woodbine also shows what Lake Forest will put up with to get a bridge right. The original was built in 1912. It had closed-spandrel shallow concrete arches on tall piers, decorative relief panels, flared pier shapes and balustrade railings that were still in good condition. The bridge sits inside the Lake Forest Historic District, which is listed on the National Register of Historic Places. The replacement had to meet modern safety standards and still look like the original.
Meeting both requirements took time. Because federal money was involved, the project went through IDOT's three-phase process. Planning ran from 2012 to 2024 and included review by the City's Historic Preservation Commission, which issued a Certificate of Appropriateness for the design. Construction was planned for 2025 but slipped a year because of budget limits, and a second grant in April 2025 closed the gap. The budget came to $4.7 million: $3.7 million in grants and $1 million from the City. Patch reported in January that work would begin that month, and the City set the start for the week of January 12.
The building method was old-fashioned too. In a Civiltech project write-up, the engineering firm describes cast-in-place concrete arches poured into formwork that was made off site and largely hand-formed, the riding surface included. The ornamental precast balustrades were shaped to echo the 1912 railings. Civiltech also notes that the 24-foot-wide residential street and the tight ravine site made it hard to stage materials and get cranes in.
The City held a ribbon cutting on September 30 and declared the project complete in its October 1 update. At the October 5 Council meeting, one speaker referred to the Lake and Woodbine bridge opening this way:
"You should go see it. It's great."
The Calendar From Here
The City's dates come from two places that don't quite match. The Lake Road Bridges project page carries an October 15 update with the latest plan. Further down, the same page still lists the project as on hold with an updated schedule expected in early 2027. The staff presentation on October 5 gave the most detail. Together they line up like this:
| Timing | What's planned at Lake & Spruce | Source |
|---|---|---|
| Monday, Oct. 19, 2026 | Channel stabilization scheduled to begin | City update, Oct. 15 |
| October to December 2026 | WJE supplemental groundwater fieldwork and testing | Council presentation, Oct. 5 |
| By mid-November 2026 | Channel stabilization expected complete | City update, Oct. 15 |
| November 2026 to "this winter" | Target to reopen Lake Road at Spruce | Council presentation; City update |
| February 2027 | Possible design-build award brought to Council | Council presentation, Oct. 5 |
| Around March 2027 | Dunnet Bay remobilizes to finish the ravine work and replace the deck | Council presentation, Oct. 5 |
| August 2027 | Possible completion, earlier than the September estimate staff gave before | Council presentation, Oct. 5 |
The winter work has three parts: gabion baskets along the north side, stone placed in the channel between and around them, and seeding to encourage natural stabilization. Staff had first expected to clean up and reopen the crossing in December. Because Dunnet Bay could come back sooner, the target moved up to November.
Treat any reopening this winter as temporary. The deck replacement still has to happen, and it depends on what the new groundwater data shows. The City's construction plan calls for Lake Road to be closed to vehicles and pedestrians at the bridge while work is underway. Plan around a second closure once crews return next spring.
Getting Around Until Then
During construction, the City has kept local access open on both sides of the bridge and maintained driveway access. Clearly marked detour signs guide drivers around the work zone. The City's detour diagram labels Sheridan Road, Woodland Road and Deerpath Road among the streets around the work zones. The current map is posted on the project page.
The stretch matters for more than through traffic. Forest Park Beach is at 801 N. Lake Road, with its fishing pier, boat launch, walking paths and boating center. On weekdays, crews may work from 7 a.m. to 8 p.m. If weekend work is needed, it runs from 8 a.m. to 6 p.m. Some equipment and materials may be parked along the road.
The City sends project alerts by email or text to anyone who registers at cityoflakeforest.com/enotify. The groundwater findings due this winter will decide how much work the ravine needs, and the next closure dates will come out of that.
On the east side, a project like this can shape daily life for a full year: the commute, the beach run, the walk you take when guests are in town. If you live along Lake Road and want to talk through how the 2027 timeline might affect your own plans for selling, buying or simply staying put, Megan Mawicke is glad to help. Let's Connect.